Norned (700 MW): Positive test results - available from week 1921-04-2008 12:34
INCI
Testing of the NorNed cable connection between Norway and the Netherlands
has endured for one and a half weeks. The results so far are affirmative,
Statnett told Nord Pool.
During the previous days power has been transmitted in both directions
between the Netherlands and Norway, up to approximately 620 MW in direction
of the Netherlands. The trials have included ramping of power, going from
low to high power transmission and down again and change of power
direction.
Both high and low power testing will be continued in the coming weeks. High
power test schemes for levels from 100 MW up to 700 MW will be published on
TenneT’s website and as urgent market message (UMM) to Nord Pool Spot
(NPS).
Depending on the outcome of the remaining tests, Statnett and TenneT aim to
make NorNed available for the market in the second week of May. TenneT and
Statnett will provide regular updates on this information.
EUROPOWER